Saturday, December 15, 2012

Indian Aircraft Carrier INS Vikramaditya (Gorshkov) now expected in last quarter of 2013

As informed by the Russian side the delivery of the aircraft carrier INS Vikramaditya (Gorshkov), after completion of repairs and sea trials, would be made in the last quarter of 2013. The aircraft carrier was subjected to extensive trials for the first time for 108 days from 8th June 2012 to 23rd September 2012, with a part of the Indian crew on board, undergoing training during the sea trials.

While a substantial scope of ship's equipment and aviation trials were completed during this period, the main propulsion plant trials to full power could not be completed due to defects encountered on boiler section. Rectification of the defect is likely to take six months.
Liquidated Damages (LD) clause for delays in delivery is incorporated in the contract. As per contract, LD is to be ascertained and levied within six months of ship's delivery.

The Russian side has been requested to take up necessary measures to ensure delivery of ship in the last quarter of 2013.



This information was given by Defence Minister Shri AK Antony in a written reply to Dr.ChandanMitrain Rajya Sabha today.